First stage columns complete. Grade beam preparations in progress.

We are currently a fee days behind schedule on this project due to the bad weather we have been having in the area recently.   Fortunately the site has not suffered from the flooding that there has been in some other areas in the region, but nevertheless, the rain has still had an impact.    However, we have now completed all of the first stage columns and are up to ground level.  Today an excavator back filled all of the footing holes, so moving forward with the project, the rain should be less of an issue.   Tomorrow we will begin to install the steel cages for the grade beams, which we have been preparing under cover during the rain.